WHAT THIS IS
Six crews of tiny minds work the same coalfield. Each has ONE setting:
how much roof safety it insists on before it will cut. Everything they
earn or lose follows from that number.
The ground is real. 520 surveyed underground workings from the
West Virginia Geological Survey, mined 1907–2008, across 15 coal
seams stacked over each other. The pale shapes are what previous crews
already took. The dark ground between them is what is left.
The physics is real. Pillar loading by tributary area, pillar
strength by the Obert–Duvall relation, safety factor as strength
over stress. Deeper ground needs fatter pillars, and fatter pillars mean
less coal. There is no free lunch.
Nobody knows where the coal is. What is mapped is what earlier
crews already took out. Beyond that edge is unknown — which is true
in reality, and is the whole hunt.
WHAT A CREW CANNOT DO
A crew cannot read the true strength of the rock. It reads the roof the
way a real miner does — sounding it, watching how the coal cuts
— and that reading is noisy. It decides on what it can see,
and the ground settles up afterwards.
Roof bolts help, cost money, and hold about four times in five.
Support reduces the chance of a fall. It does not abolish it.
WHAT THE SIM FOUND
The pillar margin you need tracks how well you can read the roof.
Sweep the crew's reading error and the best stance moves with it:
| reading error | best factor |
recovery |
| perfect | 1.5 | 59.5% |
| ±15% | 1.5 | 59.5% |
| ±30% | 1.7 | 56.7% |
| ±45% | 2.0 | 53.2% |
So
the physics sets the floor and the uncertainty sets how far above
it you must sit — two different things. Reading the roof
perfectly is worth
+16%, and lets a mine run about six points
thinner on the pillar at the same risk. Better assessment buys
extraction, and this says how much.
The outside check. With a perfect read the sim settles on
1.4–1.5 at every depth from 60 to 285 m — from tributary
loading and pillar strength alone, with no knowledge of industry
practice anywhere in the code. Published retreat-mining guidance
(ARMPS, NIOSH) uses a design stability factor of 1.5 for cover to about
198 m, and the 2010 deep-cover revision keeps 1.5.
Two caveats:
the deepest seams here are past that 198 m line, and this sim has no
barrier pillars — which is what the deep-cover guidance leans on.
Below about 1.4 there is no tradeoff at all. The reckless crew
does not buy coal with the safety it gives up. It misreads workable
ground and backs out of it, then drops roofs on what it does take:
less coal, less money, and the collapses. The two failures are not
symmetric either — beating the reckless crew is worth +158% to
+384%, beating the timid one +5% to +12%. Excess caution is cheap.
Recklessness is ruinous.
WHAT WAS CLAIMED FIRST, AND WAS WRONG
The first headline was “the middle wins.” It had been
checked three ways — long horizon, six seams, the asymmetry
— and all three were real and all three were beside the point,
because every run shared one unexamined constant: the crew's
reading error was hardcoded, and the “winning band” sat
just above it.
Three careful checks inside the same assumption prove nothing. It took
someone outside the experiment to pick the right variable to sweep.
MODELLED, NOT MEASURED
The workings, the seam, the year and the mine name come from the survey.
Depth and seam thickness are modelled — those layers carry
plan geometry and no elevation, so the spacing is a stated constant
rather than a measurement. Said plainly so nothing here is mistaken for
data it is not.